Alstom to modernise air preheater at Haapavesi power plant

29/03/2011

Alstom Power has concluded an agreement with Kanteleen Voima Oy on an air preheater modernisation at the Haapavesi power plant in Northern Finland.

The modernisation includes removal of the old radial sealing system of the air preheater plus engineering, materials (mechanical parts, electrical actuators, measurement equipment) and installation of Alstom’s sensor controlled radial sealing system.

This modernisation project will improve the energy efficiency of the plant by significantly decreasing the direct air leakage from the air preheater. The execution of this modernisation project will start in the beginning of April 2011 and it will take 4 weeks at the site.

The Haapavesi power plant is built in 1989 and owned by Kanteleen Voima Oy since December 2006. The owners, 25 Finnish energy companies, acquired the plant to produce electricity for their customers. The plant’s 390 MW boiler is burning mainly peat, additionally it can burn wood about 20 %, and also reed canary grass.

Alstom has for several years participated in the maintenance of the plant’s peat grinders, conveyors and electrostatic precipitator during the plant’s annual shutdown.