Alstom signs contract with Iraqi government to rehabilitate Khor Al Zubair gas-fired power station
Alstom signs contract with Iraqi government to rehabilitate Khor Al Zubair gas-fired power station
Press Contacts
Visit our media section and follow the link "Press contacts"
Alstom has signed a contract worth approximately 50 million with the Ministry of Electricity in Iraq for the rehabilitation of two units at Khor Al Zubair gas-fired power station, located in the Basrah district, south of Iraq. Each unit is based on Alstoms well proven GT13 gas turbine technology, originally commissioned in 1977.
The project scope includes the upgrade of the units compressors and gas turbines as well as replacement and upgrade of the electrical and control systems. Equipment for the project will be produced at Alstoms factories in Europe and at Alstoms Jebel Ali service unit in Dubai. Alstom is also responsible for installation and comissioning of the unit
The rehabilitation will increase the output of each unit by more than 30 MW , thus adding an extra 60 MWs to the electricity grid, when compared to their original rating. The upgrade will also increase the power plant efficiency and extend the life of the units significantly. The first rehabilitated unit will be reconnected to the Iraqi electricity network in 2012 and the second unit will be connected before the summer peak of 2013.
This is Alstoms second rehabilitation project signed in recent times to rebuild Iraqs energy infrastructure. Alstom is currently also rehabilitating unit 1 of the Najaf gas-fired power station, south of Baghdad, which when completed will contribute again an output of 60 MW to the Iraqi electricity network. In December 2011, Alstom also signed a contract to build the 728 MW Al Mansuriya gas-fired power plant in the Diyala Governorate, northeast of Baghdad, expected to be in operation by early 2013.
Press Contacts
Sapna Lalwani (Alstom Thermal Power) Tel +41 79 486 3798