Endesa in Spain shows continued confidence in ALSTOM Power
Sweden AB in Växjö

Press Contacts

Visit our media section and follow the link "Press contacts"

- The order, which is worth approx. SEK 47 million, is a
continuation of the agreement which was signed already in
December, 2003 and comprises a reconstruction and extension of
the existing electrostatic precipitator this time as well, at
this point for boiler 3. The previous order, which concerned
the electrostatic precipitator for boiler 4, has been
accomplished today. This reconstructed and extended
precipitator has been operating since the end of the summer and
complies well with the customer's emission requirements,
according to salesman Björn Svensson.

- The installation starts in mid-July next year and is to be
completed in the end of November, 2006. I hope that we at that
time already have been able to report about precipitators for
the remaining two boilers, Björn concluded.